Method change
Aggregate waste no longer includes compaction
The aggregate allowance used to be a flat 10% that was really the material settling. Now every aggregate carries its own compaction figure — 20% for base rock with fines, 8% for clean stone — applied to the finished volume before waste, and the waste allowance covers only real waste: the unfinished edge, what stays in the barrow, ungraded ground. Keeping both at 10% would have counted the same thing twice and over-ordered.
Read from MaterialsEstimator, Aggregate depth and compaction practice survey